Sprint 1

After using the first two weeks to get started and working with the first presentation, we have now began to properly work with the sprint system. Finding bigger tasks to work with this early can be quite difficult, therefore every member gets a couple of smaller tasks to complete.

Sprint Summary:

Task Table
Name Task Comments
Kasper Begin with user stories and use cases. Did not manage to complete due to sickness, will continue next week.
Eirik Complete the webpage design, so that it only needs to be updated with continous information. Framework is complete, frontpage is finished.
Kristian T Work with the risk analysis and redefining the requirements. Quite large tasks, still in progress.
Kristian M Fix minor problems and adjustments in overleaf report. Also do requirements for electrical components. Fixed everything in overleaf. Requirements for components is still in progress.
Ruben Help Kristian with both requirements and risk analysis. Also fix the logo for merch purchase. Tasks still in progress.
Ulrik Implement the contents from the first presentation into the report. Most of it has been implemented, but needs more time to elaborate the task decomposition.